NJ’s energy future is challenged; PJM generation queue is backlogged; PSE&G has solutions

February 2025

PSE&G processes customer and generator interconnection requests in a timely manner to support customer reliability and affordability and align with NJ’s clean energy and other public policy goals.

 

PSE&G leads the way in the state in addressing customer requests to connect to the grid whether that’s solar requests, interconnecting generators connecting to the high voltage system or large and complicated customer connections. A lack of electric generation in the state poses a risk to NJ customers, PSE&G delivers solutions.

The problem: The PJM queue has historically been backlogged. However, PSE&G is not backlogged in processing any queue-related study requests. We process study requests in a timely manner – doing what’s in the best interest of our customers seeking to interconnect to the transmission grid.

Given the significant reliability concerns associated with not having enough generation capacity on the PJM system, it’s important to get generators hooked up quickly. PSE&G is doing its part and not delaying interconnection requests to the transmission grid. Timely and efficient processing helps to bring more generation online to address resource adequacy concerns.

PSE&G has nine PJM projects in progress and 100% of the projects are on schedule for all PSE&G related work. These projects include 835 MW of storage and 12MW of solar generation. PSE&G also is aware of eight projects submitted to PJM awaiting PJM’s instruction to begin the study process in 2026. These projects include approximately 1700MW of proposed Solar, Storage & Offshore Wind. (As of 3/27/25) Consistent with its past support of PJM interconnection requests, PSE&G expects to deliver all necessary studies to PJM on time. (See tables below and source: Serial Service Request Status)

Furthermore, PSE&G leads the way on solar energy in New Jersey.

PSE&G provides timely Net Electric Meter interconnection application reviews for interconnection to PSE&G’s distribution system with a high rate of approval. PSE&G processed 12,213 net meter applications in 2024 and approved 97.8%. In the 12 months ending Feb. 28, 2025, PSE&G processed 11,795 net meter applications, supportive of the rapid deployment of generation and our commitment to clean energy. Despite the significant number of applications, average cycle times remain low.

PSE&G Net Electric Meter Application Statistics as of 2/28/2025

Resources available include:

Solar connections to distribution grid:
https://www.njcleanenergy.com/renewable-energy/project-activity-reports/project-activity-reports

Company

Total System Size (kW-DC)

% of Total

Installations

% of Total

PSE&G

2,409,729

47.4%

96,259

44.9%

AC Electric

811,720

16%

55,039

25.7%

JCPL

1,699,124

33.4%

58,971

27.5%

Orange & Rockland

50,963

1%

1,514

0.7%

Other

111,312

2.2%

2,496

1.2%

Total

5,082,848

 

214,279

 

Solar: Installed capacity as of: 2/28/2025

 

PJM Interconnection Requests with PSE&G


PJM: Current interconnection requests as of 2/28/2025

 


PJM: Current interconnection requests as of 2/28/2025